ModelRisk needs to be installed in order for the model to work.
An example of a Monte Carlo simulation risk analysis model for project risk management
Technical difficulty: 1
Schedule risk analysis uses the same principles as cost risk analysis for modelling general uncertainty and risks and opportunities. However, it must also cope with the added complexity of modelling the interrelationships between the various tasks of a project. The examples described here look at the simple building blocks that typically make up a schedule risk analysis and then shows how these elements are combined to produce a realistic model. These examples are useful for understanding the basic ideas of project schedule risk analysis. However, for risk analysis of projects of any real level of complexity (say more than 30 tasks) it is advisable to use the Tamara software instead. A project plan consists of a number of individual tasks. The start and finish dates of these tasks can be related in a number of ways:
Replace each fixed task duration with a probability distribution — for example Triangle(minimum, most likely, maximum) — keep the finish-start logic in ordinary Excel formulas using MAX for merge points, and run a Monte Carlo simulation with an add-in such as ModelRisk. The output is a distribution of completion dates: read the P80 date (the date with an 80% chance of being met) rather than a single deterministic finish. The four example models on this page follow exactly that pattern and are free to download. They are built with ModelRisk functions, but the modelling logic — distributions on durations, precedence links in formulas, risks as conditional branches — is the same in any Monte Carlo add-in for Excel. If you are comparing add-ins for schedule work, our guide to the @RISK alternatives covers the options, and ModelRisk's built-in converter opens existing @RISK models directly. To find out which tasks actually drive the completion date, run a sensitivity (tornado) analysis on the simulated schedule. For schedules beyond roughly 30 tasks, a spreadsheet network becomes hard to audit — that is the point to move to Tamara, our dedicated project schedule and cost risk tool, which imports Primavera P6 and Microsoft Project plans directly.